News
2022-06 progress at Nutrient Farm
Nutrient Farm’s Greenhouse is the first building in the world to receive a triple-layer of ETFE glazing. ETFE glazing allows for full spectrum UV sunlight for our produce, making it...
2022-06 progress at Nutrient Farm
Nutrient Farm’s Greenhouse is the first building in the world to receive a triple-layer of ETFE glazing. ETFE glazing allows for full spectrum UV sunlight for our produce, making it...
2022-05 progress at Nutrient Farm
Greenhouse: All of the trim work has been completed. Next will be the installation of the overhead and pedestrian doors. We still have to clean up some building materials,...
2022-05 progress at Nutrient Farm
Greenhouse: All of the trim work has been completed. Next will be the installation of the overhead and pedestrian doors. We still have to clean up some building materials,...
2022-04 progress at Nutrient Farm
Greenhouse: The Insulated Metal Panels have been completed and the installation of the trim has begun. These are the green thin sheets of steel run on the outside edge...
2022-04 progress at Nutrient Farm
Greenhouse: The Insulated Metal Panels have been completed and the installation of the trim has begun. These are the green thin sheets of steel run on the outside edge...
2022-03 progress at Nutrient Farm
Greenhouse Update: The steel framing of the Nutrient Farm greenhouse is complete and installation of Insulated Metal Panels (IMP) has begun. The IMPs being 4” thick will serve...
2022-03 progress at Nutrient Farm
Greenhouse Update: The steel framing of the Nutrient Farm greenhouse is complete and installation of Insulated Metal Panels (IMP) has begun. The IMPs being 4” thick will serve...
2022-01 progress at Nutrient Farm
Greenhouse update: Snow mitigation has slowed construction, but the structural steel frame of the greenhouse is nearly complete! Each beam, carefully secured in place, will soon be accompanied by...
2022-01 progress at Nutrient Farm
Greenhouse update: Snow mitigation has slowed construction, but the structural steel frame of the greenhouse is nearly complete! Each beam, carefully secured in place, will soon be accompanied by...
2021-12 progress at Nutrient Farm
Greenhouse The first structural steel components have been erected since our first snow. It’s a slow, careful process, transporting each beam to be secured in it’s final resting place. There...
2021-12 progress at Nutrient Farm
Greenhouse The first structural steel components have been erected since our first snow. It’s a slow, careful process, transporting each beam to be secured in it’s final resting place. There...